Approval for New Project or Major Modification – Consent Requirements
ES Required |
No ES Required |
Action Needed
|
|||
>12 months (depends on size of development)
|
As early as possible |
Determine requirement for an Environmental Statement (ES) by submission of Production Operations Application (PRA) (Note: An ES is mandatory for all new fields and for new or increased production of over 500 tonnes of oil or 500,000 m³ gas per day. | |||
Undertake informal consultation with statutory consultees, DESNZ, JNCC and MS/CEFAS. | |||||
Identify if development occurs in vicinity of any habitats or protected species under EU Habitats Directive. Additional measures and a Habitats Regulatory Assessment may be required. | |||||
n/a |
Undertake Environmental Impact Assessment (EIA) and prepare ES. | ||||
6 months |
Apply in writing to DESNZ for Consent to Locate for fixed installation. | ||||
n/a |
Prepare environmental information section of PRA. | ||||
n/a |
4 months |
Submit Production Operations Application (PRA) along with Application for Consent (PON16). | |||
3 months |
n/a |
Submit ES along with Application for Consent (PON16). | |||
Project Approval |
Also see summary tables for Production Consents and New Pipeline if appropriate.
|
Key Compliance
Ensure all commitments made within ES submitted to DESNZ are met with in detailed design and subsequent implementation of new project or modification. |
|||
Ensure all production or other consents are met (see Production Consents) |